Industrial and Simulated Manufacturing Projects

The below manufacturing examples are taken from work completed at the University of Portsmouth, and Caterpillar.
Projects cover: manufacturing-system design, production optimisation, digital-twin modelling, vision systems and production support.
N.B. Examples of manufacturing projects completed at Hevasure can be found under "CAD > Hevasure Aquila 2".

Design and Digital Twin Optimisation of a Hybrid Flow Manufacturing System for a Hydraulic Disc Brake Caliper

Academic project

Manufacturing Systems · Enterprise Dynamics · 2026

Project overview

A hybrid flow manufacturing system was developed for an aluminium-housing hydraulic disc brake caliper assembly. The proposed system combined parallel CNC machining, manual assembly and in-line pressure-decay testing.

The system was designed around a target output of 1,000 units per day and assessed using takt-time analysis, capacity calculations, line balancing, reliability inputs and defect-recirculation logic.

Digital-twin model

The production system was modelled in Enterprise Dynamics. The model included parallel CNC resources, manual assembly, leak testing, rework routing, internal logistics, palletising, an RFID gate and COBOT-assisted handling.

A live Excel dashboard layer was used to record quality and production KPIs without changing the routing logic of the simulation.

Key findings

CNC machining was identified as the governing constraint. Under the model assumptions, availability improvements produced a greater output increase than further reductions in downstream cycle times.

The project demonstrated that targeted Industry 4.0 deployment should focus on fault detection, maintenance response and availability recovery at the governing resource rather than applying digital monitoring uniformly across the line.

Methods and tools

Enterprise Dynamics Digital twin Takt-time analysis Line balancing RFID COBOTs Excel dashboards Industry 4.0

Available evidence

The public report records the system-design process, capacity basis, simulation structure, scenario testing and final conclusions.


Project images

Proposed facility layout for the hydraulic disc brake caliper manufacturing system
Proposed facility layout
Enterprise Dynamics baseline digital twin of the proposed manufacturing system
Enterprise Dynamics baseline model
Quality and production dashboards linked to the manufacturing digital twin
Quality and production KPI dashboards
Final optimised manufacturing-system layout in Enterprise Dynamics
Final manufacturing-system layout

Axle Optimisation

Industrial project · Caterpillar Inc.

Capital expenditure project · March 2025 – July 2025

Redesign of an axle value stream to support the transition from two shifts to one shift while retaining production throughput.

The work included planning and de-risking the relocation of an IPV vision-system station, production-station setup, tool configurations and the installation of large-screen production reporting linked to the manufacturing execution system.

Capital expenditure Value-stream optimisation Vision systems MES reporting Computer networking Kaizen

IPV Vision-System Upgrades and Software Beta Test

Industrial project · Caterpillar Inc.

July 2024 – July 2025

Production support for newly introduced image-inference software used by site vision systems. The work involved investigating production issues, supporting software patches and developing a standard configuration and installation package for site-wide upgrades.

The project combined manufacturing support with IT networking and cybersecurity awareness. Internal configuration details are intentionally excluded from the public portfolio.

Vision systems Image inference Software beta testing Computer networking Cybersecurity Kaizen

Output Transfer Gear Line Optimisation

Industrial project · Caterpillar Inc.

Capital expenditure project · April 2025 – July 2025

Consolidation of two production lines into a single line capable of supporting two separate products.

The project included production-station setup and design, health-and-safety sign-off activities, manufacturing-execution-system configuration, fixture design and the preparation of standard work.

Capital expenditure Production-line consolidation MES configuration Fixture design Creo Parametric Standard work

Publication Notes

Industrial project descriptions are limited to publishable high-level information. Internal layouts, production data, software configurations and commercially sensitive documents are not included.